The Development Bureau announced on Monday (March 14) that it will grant an extension of time for government works contracts and the building covenant (BC) period under land leases of private development projects for up to six months.
The decision was made due to the substantial impact caused by the fifth wave of the COVID-19 epidemic on the development and construction sectors.
Development Bureau announced that :
(i) for all government works contracts in progress, the Government will flexibly handle requests from contractors for extension of time due to the impact of this wave of the epidemic, for up to a maximum period of six months; and
(ii) for all leases with unfulfilled BC as at today, the original expiry of the BC period may be extended at nil premium by up to six months.
The bureau said: “The above measures aim to provide upfront certainty to various professions and contractors in the industry, so as to minimise unease and pressure that may be generated by the existing contractual deadlines and BC periods. These measures could also provide an additional buffer for the industry and relevant government departments so that they would have more capacity to cope with the epidemic and participate in anti-epidemic work.”
Government last extended the BC period for land leases in April 2020, but this is the first time that an extension of time has been granted for works contracts.
Quite what “flexibly handle” requests for extension of time will mean practically, for example which period the 6 months will apply to, why a maximum of 6 months, or how the extension will be granted, have yet to be elaborated.
Contractors will be incurring very substantial costs. While there will be a general sense of relief to hear that the risk of liquidated damages has been eased, they are unlikely to be able to get by with an extension of time alone, and will undoubtedly be lobbying Government to consider granting both time and money, and looking for ways to recover these costs through the contract.
If you would like to discuss the implications of these measures for your projects, please do not hesitate to get in touch with Ian Cocking, Dennis Wong or your usual contact.