By Ian Cocking, Partner
Overview
Adjudication is a topic which has recently drawn the attention of many, once again, following the .
There are two types of adjudication, namely statutory and contractual adjudication. Statutory adjudication is a mandatory step included in SOP legislation for construction disputes in a number of jurisdictions, such as the UK and Singapore. Contractual adjudication is merely based on the terms of the agreement. Hong Kong has decided to start with contractual adjudication with the aim of one day migrating to the statutory model
This article considers the main differences between the contractual adjudication model that is being rolled out and a statutory regime, and goes on to explain why legislation should be introduced to put adjudication on a statutory footing as soon as possible.
Contractual adjudication is clearly a step in the right direction. . This can leave the claimant without remedy for years. Viewed through this lens, the current scheme has to be an improvement, but there are several inherent shortcomings that make it pale by comparison to a conventional statutory scheme.
Main contractors, sub-contractors, consultants and suppliers are highly vulnerable to disputes and payment delays. For example, during the industry wide survey conducted by the Hong Kong SAR Government and the Construction Industry Council in 2011, it was found that the average outstanding payments per annum amongst main contractors, sub-contractors, consultants and suppliers ranged from 5 – 12 % of their total business receipts.[1]
Needless to say these problems apply to public and private sectors alike. The first key difference between contractual and statutory adjudication is that the current contractual . Therefore, given that payment problems are industry-wide, contractual adjudication is no substitute for the urgent need for inclusive legislation covering all participants in the public and private sectors, including consultants and suppliers.
The Contractual Scheme
Technical Circular (Works) No. 6/2021 (“Technical Circular”) issued by the Development Bureau (“DEVB”) on 5 October 2021 only incorporates mandatory SOP conditions into all new public works contracts and sub-contracts. Additional Conditions of Contract (“ACC”)/ Special Conditions of Contract (“SCC”) amend the General Conditions of Contract, including NEC forms accordingly. DEVB updated the Library of Standard Amendments to NEC 4 in September 2022. It is said that through the experience gained in the public sector, it is hoped that legislation (which has been drafted) can be implemented smoothly covering the public and private sectors. However, no definitive time scale has been provided and Hong Kong will still not have broad based adjudication covering the public and private sectors until there is legislation
The between Hong Kong’s contractual adjudication and statutory adjudication are:
- Enforcement of adjudication decisions will not be directly by the Court. Court enforcement is effectively replaced by a right to apply to the employer for direct payment;
- The Court has not been given direct power to set aside adjudication decisions. An aggrieved party must challenge the decision in arbitration, which will not be until long after completion;
- There is no statutory register of adjudicator nominating bodies (“ANBs”). The selection of ANBs is from a register maintained by DEVB (“Register”).
This is not to say that an aggrieved party will be without any potential remedy through the Courts, but any rights will be subject to whether/what jurisdiction the Court has in the circumstances (if any).
Payment and Adjudication Process
Before delving further into the differences, the key features of Hong Kong’s contractual adjudication are highlighted below. These are mirrored by the proposed legislation.
Firstly, the ACC/SCC include the following :
- Payment response and payment shall be made within 30 and 60 days respectively from the date of payment claim (as a matter of contract);
- Conditional payment provisions shall be rendered ineffective and unenforceable (but only as a matter of contract);
- Claimant may refer a payment dispute to adjudication and the adjudicator shall deliver a decision within 55 working days from the date of his appointment, which may be extended by the agreement of the parties, which is far longer than most statutory regimes;
- Claimant may exercise a right to suspend/ slow down if an admitted or adjudicated amount is not paid, but again this right is only afforded as a matter of contract between the two contracting parties.
There has been some controversy as to whether the scope of adjudication should extend to extension of time awards (“EOT”) as well as time-related payment issues (as it does in most statutory regimes). Under the present scheme, it has been decided that in Hong Kong under the contractual model as follows:
- An adjudicator shall have the jurisdiction to decide time-related costs forming part of the payment dispute;
- In so doing, the adjudicator shall have the jurisdiction to decide EOT entitlement;
- The adjudication decision on time-related costs forming part of the payment dispute is binding on an interim basis, but the EOT so decided by the adjudicator is not.
However, this is a matter of construction of the contracts. The parties’ ultimate rights to seek/ challenge EOT decisions rest with arbitration. It is expected that the legislation, when introduced, will also follow the same formula restricting the adjudicators’ jurisdiction to deciding time-related costs only.
Enforcement
Under the contractual model, if the adjudicated amount is unpaid, the sub-contractor has 2 express options; either to seek direct payment from the employer, or, to exercise its contractual right to suspend/slow down its works.
With respect to the direct payment option, this relies on there being an unbroken chain of contracts incorporating the SOP Provisions under relevant subcontracts. Upon submission of an application by the sub-contractor to the employer evidencing an outstanding adjudicated amount, the sub-contractor has to wait for 28 days or more for the employer and the main contractor to unravel the issues going down through the sub-contracting chain to see, for instance, if a sub-contractor at any higher tier has become bankrupt and would therefore be unable to pay. Also, payment to the sub-contractor is not guaranteed because This rather convoluted procedure is in stark contrast to the ability of a sub-contractor to simply go to Court for enforcement as would be the case under a statutory system
As regards the suspension or slowing down route, the sub-contractor simply needs to serve on the main contractor a notice of intention at least 5 working days before the date (“intended starting date”) it intends to suspend or slow down the work progress and to take reasonable steps at least 5 working days before the intended starting date to make the employer and the main contractor aware of such notice of intention. As a matter of contract, the sub-contractor will not be liable for any loss and damages suffered by others and will be entitled to EOT and prolongation costs as a result of the suspension. However, other sub-contractors/ suppliers will not enjoy any consequential rights or privileges, and this will bring enormous pressure on main contractors in particular who may be completely unconnected with the dispute. It is less likely that sub-contractors would have to resort to these tactics if Court enforcement was available. This is because the threat alone of Court proceedings would usually be sufficient to trigger payment
Main Contractor’s Obligations
The contractual regime is wholly reliant upon a pristine chain of contracts. To ensure the SOP provisions are incorporated into relevant sub-contracts, main contractors are under express contractual obligations to take all reasonable steps to make sure sub-contractors of a lower tier are also in compliance of the provisions. However, they have no real powers to police sub-contracts of lower tiers.
Copies of sub-contract documents are to be submitted by main contractors to the Employer’s representatives for the purpose of checking that the SOP provisions have been incorporated into the sub-contracts. Main contractors are also required to report to the Employer’s representatives if any notices of adjudication have been served, or if any payment/settlement of adjudicated amounts remain outstanding. Again, these are matters in respect of which main contractors have only limited control, and depend upon how successfully the SOP have been incorporated at every tier.
Whether these obligations are practical or achievable remains to be seen, but they would be wholly unnecessary if these were statutory rights in respect of every construction contract.
The Project Office will be expected to monitor the main contractor’s performance in relation to the incorporation of SOP provisions into all sub-contracts. The main contractor may receive a warning if he fails to do so. In addition, if the main contractor fails to provide any documentary proof of compliance, the Project Office will give “poor” or “very poor” rating in the Contractor’s Performance Report. Such rating may have an adverse impact on their ability to secure future works. These sanctions are only introduced because the contractual scheme is so vulnerable to a break in the chain of SOP provisions and punish main contractors for problems which may be beyond their knowledge or control.
Security of Payment Adjudication Rules
There are 4 ANBs listed in DEVB’s Register. They are the Hong Kong Institute of Architects (“HKIA”), the Hong Kong Institute of Surveyors (“HKIS”), the Hong Kong Institution of Engineers (“HKIE”) and the Hong Kong International Arbitration Centre (“HKIAC”). Their functions include, but are not limited to, the appointment of adjudicators, facilitating the adjudication process and establishing of adjudication rules (“Adjudication Rules”). Interestingly, the ANB validity periods on DEVB’s website are stated to be from 1 January 2022 to 31 December 2024 only. It remains to be seen if other ANBs will be invited to join the Register in the future, and whether the deadline has any significance in relation to any anticipated enactment of legislation. However, the current Register is only the one kept by DEVB. When legislation is introduced, a statutory register would have to be kept
NEC Contracts
Under SOP, a contractor is entitled to suspend works if there is a non-payment of an adjudicated sum. This is added as a new compensation event in Clause 60.1. The dispute resolution provisions are also amended. Note that the NEC 4 dispute resolution clauses (W clauses) incorporating adjudication provisions are not used in Hong Kong public works NEC contracts. The Hong Kong Government has drafted its own dispute resolution clause – ACC Clause G1B. This Clause G1B is also amended to tie-in with the mandatory SOP Provisions. If any party is dissatisfied with the SOP adjudication decision, it may refer the dispute to mediation, and if mediation fails or is refused, then to arbitration
In Hong Kong, NEC sub-contracts are rarely used in projects adopting NEC main contracts. NEC main contracts have a shorter cycle (35 days). Therefore, a project with an NEC main contract but other forms of sub-contract may have different payment cycles. This will create cashflow challenges that have to be carefully managed.
For the reasons explained above, if unpaid, enforcement of an adjudicator’s decision may rest on direct payment by the employer. If direct payment is not made for any reason, a sub-contractor will have to rely upon the pressures it can bring to bear upon the defaulting party by exercising a contractual right to suspend/ slow down its work. Given the need for faster paced contemporaneous decision making under NEC, neither of these options is likely to be swift or practical enough to compel prompt payment compared to direct enforcement through the Court under a statutory framework.
Conclusion
Many jurisdictions have already made statutory adjudication mandatory. Although , very few adjudications have eventuated. Whilst the attempt to introduce contractual adjudication is laudable, it is no replacement for statutory adjudication. If legislation will only be implemented based upon the experience gained from contractual adjudication, the comparison may not be a fair one.
While the precise timing of the legislation is unknown, there are some encouraging signs. According to the Legislative Council’s “Panel on Development – List of outstanding items for discussion” published in May 2022[2], the proposed timing for discussion on the legislative framework of the SOP Bill is stated to be in 2023. It remains to be seen whether implementation could move ahead of contractual adjudication experience.
[1] “Proposed Security of Payment Legislation for the Construction Industry, Consultation Document,” Development Bureau of the Hong Kong Special Administrative Region Government (June 2015), Chapter 1, paragraph 5, https://www.devb.gov.hk/filemanager/en/content_880/SOPL_Consultation_Document.pdf.
[2] “Panel on Development – List of Outstanding Items for Discussion,” HKSAR Legislative Council (17 May 2022), LC Paper No. CB(1)276/2022(01), item 14, https://www.legco.gov.hk/yr2022/english/panels/dev/papers/dev20220524cb1-276-1-e.pdf.