By Ian Cocking, Partner
The Court will read and construe the terms of the demand to call a performance bond objectively based on its plain wording and would not lightly find that the drafter intended to add or use redundant and surplus words.
It is common for contractors to provide performance bonds to employers to secure due performance of their construction projects. However, disputes often arise when the employer seeks to call the bond, especially an on-demand bond, without proof of default. It may lead to separate court proceedings between the employer, the bondsman and/ or the contractor, including urgent and a costly injunction application to stop the bond payment.
Readers may recall that in April 2020, in the case of West Kowloon Cultural District Authority v AIG Insurance Hong Kong Limited [2020] HKCFI 569, the Court of First instance appeared to favour an “in substance compliance” test in an on-demand bond situation. It was held that the owner’s demand for the bonded sum was valid notwithstanding that the demand covered future damages, loss, etc. which fell outside the ambit of the bond.
However, this decision has just been overturned by the Court of Appeal in West Kowloon Cultural District Authority v AIG Insurance Hong Kong Limited [2022] HKCA 975, where a stricter approach to interpretation was adopted.
Background and the CFI’s Decision
The case concerned a demand bond in the sum of HK$297,198,000 obtained by Hsin Chong Construction Company Limited from AIG Insurance Hong Kong Ltd. It was obtained in favour of West Kowloon Cultural District to secure the due performance of Hsin Chong at the “M+” construction project.
Hsin Chong had become insolvent. As a result, West Kowloon terminated Hsin Chong’s employment on the basis that a default had occurred. It has also separately demanded AIG to make payment of the full bonded sum.
Subsequently, West Kowloon applied for summary judgment against AIG and AIG applied to strike out the court action on two grounds:
- Formality issue (i.e. Whether the demands complied with the terms of the Bond when they did not identify the amount of damages sustained by reason of the default); and
- Fraud Issue (i.e. Whether the demands were made fraudulently).
Concerning the Formality Issue, AIG further complained that the demand purports to include a claim for future or prospective losses which are not within the terms of the Bond.
The Court of First Instance decided both issues in favour of West Kowloon – that the demand complied with the terms of the Bond and was not made mala fide. It was held that taking a “strict compliance” approach may undermine the certainty and reliability of on demand bonds. The terms of the bond did not require particularization or proof of the amount demanded. Since the demand did refer to damages, losses, etc. sustained, the additional reference to future damages and losses was at most redundant and a surplusage and could be ignored.
Court of Appeal’s Decision
AIG only pursued its appeal based on the Formality issue.
While the Court of Appeal held that the demand was clearly demanding the bonded sum as it related to Hsin Chong’s default under the contract, it agreed with AIG that the bond only referred to “actual or quantified amounts”. On a proper construction based on the plain meaning of the words, the bonded sum as demanded included future damages and losses, which were outside the ambit of the terms of the bond. Therefore, the demand was non-compliant with the bond and was thus invalid.
In arriving at this decision, the Court of Appeal expressly stated that, “as a matter of construction, the court normally expects the drafter to use words chosen to express a meaning and would not lightly find that he intended to add or use redundant and surplusage words”.
Accordingly, the appeal was allowed with costs of the appeal and 80% of the costs below awarded to AIG. It was also ordered that the sum already paid to West Kowloon be repaid to AIG with interest.
Conclusion
A feature of this case is that it was the surety, AIG, challenging the call on the bond. That is presumably because Hsin Chong had become insolvent and therefore AIG would not be able to recover the money paid out. Ordinarily a surety would probably pay and leave the contractor to challenge the call.
Compared with the Court of First Instance, the Court of Appeal favoured a strict legal interpretation in determining whether the demand had complied with the terms of the bond. A demand will be construed objectively based on the plain meaning of the words – and on this wording, employers cannot call a bond relying on unspecified losses they will incur in the future.
This case will be welcomed by contractors if it will deter some bond calls, and is a clear example of how substantial time and costs (as well as interest on the repaid sum) can be incurred in legal proceedings when a bond is called. Therefore, any decision to call a bond should only be made with legal advice and after careful consideration.